Less than a month after the Lower Thames Crossing team presented its low-carbon construction ambitions at the CEA-hosted CECE Congress in London, the CEA had the opportunity to see those ambitions being put into practice at one of the UK's largest infrastructure projects.
At the project's first media site tour on 24 November, taking centre stage were four Volvo A40 Electric articulated dump trucks (ADTs), supplied by SMT GB to the Bouygues Travaux Publics and Murphy joint venture (BMJV).
National Highways describes them as the world's largest electric articulated haulers in production and the first battery-powered machines in their size class to start work on site anywhere in the world.
The machines are moving aggregates for the construction of platforms and tunnel approaches for the Lower Thames Crossing, which will connect Kent and Essex through 23km of new road, including twin 4.2km tunnels beneath the Thames.
With a 39-tonne payload and a 540kWh battery, the A40 Electric is designed to match its diesel counterpart in performance, payload and tractive force. The deployment marks a significant step in bringing battery-electric technology to heavy earthmoving applications.
Creating demand for zero-emission machinery
At the CECE Congress on 29 October, Neesha Pandya, head of low carbon delivery at the Lower Thames Crossing, and colleague Michael Chester outlined the project's role as a carbon pathfinder for UK construction.
National Highways aims to make the Lower Thames Crossing the first major UK infrastructure project to achieve carbon neutrality in construction, targeting a 70% reduction against its original construction carbon baseline of 2.8 million tonnes of CO₂, with remaining emissions to be offset. Its ambition is to achieve that reduction at no net additional cost.
One of the most striking figures presented at the Congress was the estimated 63 million litres of diesel that would otherwise have been required during construction.
“We'll replace that 63 million litres with a mixture of electric, hydrogen and HVO biofuel,” said Pandya during the site visit.
Conventional diesel has not been permitted on Lower Thames Crossing construction sites since 2025, another first for a major British infrastructure project.
Around 150 zero-emission machines are forecast to be working on the project by peak construction in 2028, with Pandya indicating that there could be opportunities to increase that number as the equipment market develops.
Of particular relevance to CEA members is the project's approach to procurement. Rather than waiting for suitable machinery to become available, National Highways has incorporated carbon requirements into its tenders, using its purchasing power to give manufacturers greater confidence to invest in developing larger zero-emission machines.
At the Congress, Pandya and Chester identified five key lessons from the project: start with manageable deployments and build confidence; use procurement to accelerate adoption; secure energy early; understand costs and technical capabilities; and develop the right team and culture.
Speaking during the site visit, Phil Battle, managing director, Great Britain, at SMT GB and a CEA board director, explained how the commercial argument for electric construction equipment is changing.
The Volvo haulers are achieving five to six hours of operation, with opportunity charging enabling them to complete a full shift. At East Tilbury, GeoPura's hydrogen-powered generators provide electricity for charging, with overnight charging and top-ups during natural breaks in the working day.
“The key point with electric equipment is there's no idle time,” said Battle, estimating that 30–40% of recorded diesel engine hours can be spent idling.
For contractors, the more meaningful comparison is how many tonnes of material a machine can move during a shift.
Battle explained that the price difference between electric and conventional machinery was narrowing and that, once purchase price and operating costs were considered together, electric machines could be cheaper over the course of a project.
“We're seeing not just parity but actually the electric coming out cheaper when you run it over a project cycle.”
National Highways forecasts lower whole-life costs for the electric haulers than their diesel or HVO equivalents, although longer-term operational experience will be needed to substantiate those savings.
Battle also reported an increase in enquiries about electric machinery: “We're seeing major infrastructure projects become a lot more interested in zero emissions, not just because of the environment but because of the TCO, the total cost of operation.”
There are benefits for operators, too, with reduced noise and vibration contributing to positive feedback.
“Operators are feeding back that actually at the end of the shift they feel fresher, better,” said Pandya.
Darren Fitch, head of strategic accounts and electromobility sales Europe at Volvo CE, highlighted the industry's changing priorities: “From a technology perspective, it's no longer a steep learning curve. Now we come into the deployment learning curve.”
He added: “The Lower Thames Crossing is a showcase for low-carbon construction in action.”
“When the industry can see that firsthand, perceptions change. Projects like this don’t just demonstrate what’s possible today, they help reshape expectations for tomorrow.”
Challenges remain for the wider equipment industry, including access to power, common charging standards, residual values, battery condition, financing and the skills needed to maintain high-voltage equipment safely.
Equipment dealers will also play an increasingly important role, extending beyond machinery supply and maintenance to advising customers on energy requirements, charging infrastructure and technical training.
For CEA members, the Lower Thames Crossing is an example of how collaboration between infrastructure clients, contractors, manufacturers, equipment dealers and energy providers can accelerate the adoption of new technology.
The experience gathered over the coming years could prove particularly valuable to the construction equipment industry, establishing how zero-emission machinery performs at scale, what energy infrastructure it requires and, crucially, whether the commercial case holds across the wider construction sector.
Phil Battle SMT & Neesha Pandya LTC